Definitive permission for Wind farm N33

On May 29th, the Dutch Council of State (Raad van State) has ruled that the objections against wind farm N33 are unfounded. The department of administrative justice concluded that the plans for the wind farm comply with the current legal requirements. This means that the 35-turbine, 120MW wind farm has definitive building permissions.

Pondera Consult was responsible for N33’s EIA and permit procedures, including all necessary studies. This project was one of Pondera’s very first, and we are happy with the achieved results after almost ten years of development.

Wind farm N33 will be located in the municipalities of Veendam, Midden-Groningen and Oldambt. The developers are YARD Energy, Blaaswind BV and Innogy Windpower Netherlands. The wind farm will significantly contribute to the local, regional and national goals for the production of renewable energy.